Difference between revisions of "CalNex-JG"
From Jimenez Group Wiki
(→Tasks in preparation for CalNex-LA) |
|||
(70 intermediate revisions by 7 users not shown) | |||
Line 1: | Line 1: | ||
This page serves as documentation for organization of the Jimenez Group's participation in CalNex-LA. Do not confuse this page with [http://cires.colorado.edu/jimenez-group/wiki/index.php?title=CalNex-LA the Main CalNex-LA page] or the [http://cires.colorado.edu/jimenez-group/wiki/index.php?title=CalNex-LA_Logistics CalNex-LA Logistics page]. | This page serves as documentation for organization of the Jimenez Group's participation in CalNex-LA. Do not confuse this page with [http://cires.colorado.edu/jimenez-group/wiki/index.php?title=CalNex-LA the Main CalNex-LA page] or the [http://cires.colorado.edu/jimenez-group/wiki/index.php?title=CalNex-LA_Logistics CalNex-LA Logistics page]. | ||
+ | |||
+ | |||
+ | == Tasks after CalNex-LA == | ||
+ | |||
+ | * Repairs & upgrades | ||
+ | ** Michael: quote on upgrade of 2x pump boxes (1 w/ 3x V301 controllers + higher rating of cables) & 2x automatic valves for inlet | ||
+ | ** Carly: check with Varian on interlock signal on V70-prog_as_V301 controller (now inside pump box controlling pump 5) | ||
+ | ** Michael: make sure we have 3x working RH probes and coupling hardware and that they work (working on it) | ||
+ | ** Patrick + Amber: fix 3 us offset with PToF in lab AMS (try rebooting multiple times). Talk to Donna about software. (working on it) | ||
+ | ** Patrick: calibrate all critical orifices, decide whether we need to order more (Waiting for Art to come back) | ||
+ | ** Michael: make a couple more orifice fixtures | ||
+ | ** Michael: replenishing O'Keefe orifices and fuses | ||
+ | ** Michael: identify big stand-alone tool chest (lockable) | ||
+ | ***[http://www.sears.com/shc/s/p_10153_12605_00910600000P?prdNo=1&blockNo=1&blockType=G1 Link] | ||
+ | ***Lockable | ||
+ | ***Deep and Shallow drawers | ||
+ | ***Ball Bearing drawer slides rated to 70lbs/drawer | ||
+ | ***other stackable components if expansion is ever necessary | ||
+ | ** Amber: Check channel 0 in Lab AMS slow board (and another channel) | ||
+ | ** Modules are switched between Lab and C TPS. | ||
+ | ** follow up on filament problem with TPS software (filament would go down) -- mention to Joel, try to reproduce | ||
+ | |||
+ | |||
+ | * Completed Post CalNex-LA Tasks | ||
+ | ** Michael: Make map of east campus storage, and store location on group GPS | ||
+ | ** Michael: order 1 1000-Torr baratron (1/2" tube connection) for Lab AMS. | ||
+ | ** Michael: see when Varian guy is available after IAC (spinning, general pump stuff) | ||
+ | ** (Move them here as they are completed, so that we all know that they have been completed) | ||
+ | ** Carly: ask Thomas (cc Jose) where do we get special tool to remove module, and whether it is practical. | ||
+ | ** Carly: test interlock on HIAPER, it works | ||
+ | ** Amber + Patrick: clean lab AMS including fans (in pumps, electronics box, power supply, computer) | ||
+ | ** Carly: replace pulser flange | ||
+ | ** Carly: Replace MAB pump 5 | ||
== Tasks in preparation for CalNex-LA == | == Tasks in preparation for CalNex-LA == | ||
− | * Field kit | + | * Field kit |
− | + | ** SMPS comparison: Mike, Michael (run, analysis in progress) | |
− | ** | + | ** plywood bases for Ingrid's shelving racks? (Michael, confirm with Jose) |
− | ** | + | ** inflatable mattresses (Jose will bring 2) |
− | |||
− | |||
− | |||
− | |||
− | ** | ||
* Organization - Try to have ready by Mar 18 (next business mtg) | * Organization - Try to have ready by Mar 18 (next business mtg) | ||
** Which AMSs to bring: MAB-AMS + LAB-AMS + C-AMS | ** Which AMSs to bring: MAB-AMS + LAB-AMS + C-AMS | ||
− | |||
** AMS alternation: PAM + TD: on LAB-AMS | ** AMS alternation: PAM + TD: on LAB-AMS | ||
*** Ambient: 1min V, 1 min W | *** Ambient: 1min V, 1 min W | ||
*** PAM: same | *** PAM: same | ||
*** TD: same | *** TD: same | ||
− | *** Need to set up + test Jayne switching valves: Mike + Amber ( | + | *** Need to set up + test Jayne switching valves: Mike + Amber (in progress) |
− | *** concentrator: Sanna | + | *** concentrator: Sanna will come 1st 2 weeks, she can send concentrator to CU in advance: we will use w/ MAB (Jose, Carly emailing with Sanna) |
*** Need a set of valves for concentrator: Carly w/ yellow - Amber will show her | *** Need a set of valves for concentrator: Carly w/ yellow - Amber will show her | ||
− | *** Need to be able to step vaporizer temperatures: Carly | + | *** Need to be able to step vaporizer temperatures: Carly + Joel |
− | *** Inlet schematic for J-Group instruments: account for all fittings + tubing a priori: | + | *** Inlet schematic for J-Group instruments: account for all fittings + tubing a priori: (Mike in progress). Include how to test for leaks and flows. |
− | **** | + | **** logging computers are assigned to instruments - DONE (Mike) |
***** TSI software and Labview software can't run on the same computer | ***** TSI software and Labview software can't run on the same computer | ||
− | ** Put together 2x valve filtering system for | + | ** Put together 2x valve filtering system for inlets (3): (Delphine) (valves/tees/etc. found, set aside) |
** Which SMPSs | ** Which SMPSs | ||
− | *** One in parallel with Lab-AMS, one in parallel with MAB-AMS, one as shared calibration system ( | + | *** One in parallel with Lab-AMS, one in parallel with MAB-AMS, one as shared calibration system (comparison in progress, see above: Ingrid + Michael + Donna) |
− | + | ** OPC: Michael. software updated to report PM1, PM2.5, PM10; Mike has Igor code for analysis (see wiki) | |
− | ** OPC: Michael. | ||
** Radioactive source and chemical inventory and shipping: Michael | ** Radioactive source and chemical inventory and shipping: Michael | ||
− | ** Driving our stuff there: Michael will rent truck (Penske). | + | *** waiting on Michelle; need to do reciprocity |
+ | ** Gas requirements (current plan is to bring everything from CU; Carly, Amber will make sure we have it for packing) | ||
+ | *** zero air (1 tank at a time, probably 2 tanks total) - Amber | ||
+ | *** N2 (3 cylinders) - Amber | ||
+ | *** SO2 cal gas - Amber | ||
+ | *** research-grade N2 - Carly | ||
+ | *** research-grade Ar - Carly | ||
+ | *** research-grade Kr (2 lecture bottles) - Carly | ||
+ | ** ICARTT sharing file organization (Ingrid + Donna) | ||
+ | *** bother people about adding a sample file or readme saying they won't share data | ||
+ | |||
+ | ** Driving our stuff there: Michael will rent truck on Friday, get CIRES parking pass (Penske). | ||
*** pick up truck Saturday, May 1 | *** pick up truck Saturday, May 1 | ||
− | *** load Sunday, May 2 | + | *** load Sunday, May 2 at 10am Ingrid, Carly, Mike, Amber, Michael, Patrick, Art |
*** TO CalNex: Michael + Amber, departing Boulder May 3, arriving Pasadena May 4 | *** TO CalNex: Michael + Amber, departing Boulder May 3, arriving Pasadena May 4 | ||
*** FROM CalNex: Michael + Mike, departing Pasadena June 18, arriving Boulder June 19 | *** FROM CalNex: Michael + Mike, departing Pasadena June 18, arriving Boulder June 19 | ||
− | ** | + | |
+ | == Power Breakdown for Jimenez Trailer at CalNex-LA == | ||
+ | Will be updated when power is final - see google doc, ppt for latest | ||
+ | |||
+ | * PAM-TD-AMS related instruments | ||
+ | **Circuit 12A: 9.09 A | ||
+ | ***HR-AMS 6.36 A, 700 W instrument | ||
+ | ***Thermo Denuder (TD) 2.73 A, 300W | ||
+ | **Circuit 10B: 8.31 A | ||
+ | ***PAM 6.8 A, 750 W (total, including lamp power supplies, MFCs, O3, RH, and SO2 monitors) | ||
+ | ***Grimm OPC 0.2 A, 20 W | ||
+ | ***TSI DMA #1 0.81 A, 90 W | ||
+ | ***CPC 3010 #1 0.3 A, 33 W | ||
+ | ***DustTrak 0.16 A, 18 W | ||
+ | *Shared Circuits | ||
+ | **Circuit 10A: 12.9 A | ||
+ | ***Gast Pump for Perma Pure (by-pass) 5.45 A, 600 W | ||
+ | ***Gast Pump for DT and OPC (by-pass) 5.45 A, 600 W | ||
+ | ***UHSAS 2 A, 220 W | ||
+ | **Circuit 11: 16.35 A (butanol exhaust) | ||
+ | ***Gast Pump (CPC 3010 #1) 5.45 A, 600 W | ||
+ | ***Gast Pump (CPC 3010 #2) 5.45 A, 600 W | ||
+ | ***Gast Pump (MAB Atmozier) 5.45 A, 600 W | ||
+ | *MAB-Concentrator Related Instruments | ||
+ | **Circuit 12B: 9.88 A | ||
+ | ***Soft-Ionization (MAB) HR-ToF-AMS 6.36 A, 700 W instrument | ||
+ | ***MAB Power supplies 0.53 A, 58 W | ||
+ | ***MAB Discharge Supply 0.25 A, 27.5 W | ||
+ | ***Concentrator Electronic Box 2.74 A, 300 W (estimated) | ||
+ | **Circuit 7: 15.7 A | ||
+ | ***Concentrator Chiller 10.45 A, 1150 W | ||
+ | ***Concentrator Saturator Heating Tape 5.24 A, 576 W | ||
+ | **Circuit 8: 15.21 A | ||
+ | ***TSI DMA #3 0.81 A, 90 W | ||
+ | ***CPC 3010 #2 0.3 A, 33 W | ||
+ | ***Gast Pump (by-pass for MAB) 5.45 A, 600 W | ||
+ | ***UV-APS 3.2 A, 350 W | ||
+ | *Independent Circuit | ||
+ | **Circuit 9: 6.86 A | ||
+ | ***TSI Water CPC 3786 0.6 A, 66 W | ||
+ | ***TSI DMA #2 0.81 A, 90 W instrument | ||
+ | ***Gast Pump for Atomizer 5.45 A, 600 W | ||
+ | |||
+ | |||
+ | |||
+ | *Updated(AMO 1635 PDT 16 May 2010) | ||
== Distribution of tasks while in the field == | == Distribution of tasks while in the field == | ||
Line 48: | Line 130: | ||
** Thermal Denuder (Amber -- Mike will train Jose) | ** Thermal Denuder (Amber -- Mike will train Jose) | ||
* MAB-AMS (Carly) | * MAB-AMS (Carly) | ||
− | * C-AMS ( | + | * C-AMS (probably won't bring) |
− | ** | + | ** if bring, don't plan to operate, keep pumped in trailer |
− | * SMPS, CPC on Carly's Inlet (operated by Mike, data reduction in field) | + | ** possibly Darin could ship if we're desperate |
− | * SMPS, CPC on Amber's Inlet (operated by Mike, data reduction in field) | + | * SMPS, CPC on Carly's Inlet (operated by Mike, data reduction in field Michael/Ingrid) |
+ | * SMPS, CPC on Amber's Inlet (operated by Mike, data reduction in field Michael/Ingrid) | ||
* SMPS, CPC for calibration (operated as needed - AMS operator) | * SMPS, CPC for calibration (operated as needed - AMS operator) | ||
− | * Calibration CPC for ambient data (Mike) | + | * Calibration CPC for ambient data (Mike, data reduction in field Michael/Ingrid) |
− | * OPC (Michael w/Ingrid) | + | * OPC (Michael w/Ingrid; igor code from Mike) |
* DustTrak w/ PM1 inlet (Michael w/ Mike) | * DustTrak w/ PM1 inlet (Michael w/ Mike) | ||
* TAG-AMS (Mike + Jose will support operation) | * TAG-AMS (Mike + Jose will support operation) | ||
+ | * UHSAS (Ping would bring, Delphine?) | ||
+ | * UV-APS (Alex could send, would do data) | ||
* Downloading data from other instruments and model, making graphs and posting them (Ingrid) | * Downloading data from other instruments and model, making graphs and posting them (Ingrid) | ||
* Uploading and plotting data in real-time: Ingrid, Donna | * Uploading and plotting data in real-time: Ingrid, Donna | ||
* Support: Delphine | * Support: Delphine | ||
+ | |||
+ | == Logging & pumping summary == | ||
+ | * Logging computers: [duty cycles] | ||
+ | ** Laptop 1: LabVIEW only, PAM inlet (best computer). | ||
+ | *** Ozone monitor [low] | ||
+ | *** Grimm [medium] | ||
+ | *** DustTrak [low] | ||
+ | *** RH monitor [low] | ||
+ | ** Laptop 2: TSI AIM, PAM inlet | ||
+ | *** Long-column 3010-based SMPS system | ||
+ | ** Laptop 3: LabVIEW only, PAM inlet | ||
+ | *** SO2 monitor (need more info on serial feed) | ||
+ | *** lamp control (ditto) | ||
+ | ** Laptop 4: LabVIEW only, MAB inlet | ||
+ | *** TSI flowmeter on MAB SMPS [low] | ||
+ | *** Yellow switching valve system [low] | ||
+ | *** Can be one of the old black laptops | ||
+ | ** Laptop 5: LabVIEW only, PAM inlet | ||
+ | *** Jayne switching valve system [low-medium] | ||
+ | *** TSI flowmeter on PAM SMPS [low] | ||
+ | ** Labtop 6: TSI AIM, MAB inlet | ||
+ | *** Long-column 3786-based SMPS system (MAB) | ||
+ | |||
+ | * Gast lab pumps | ||
+ | ** Pump 1: 3010 scanning (ON MAB inlet - circuit 11, butanol exhaust) | ||
+ | *** dP >= 500mb | ||
+ | *** 1.0 lpm | ||
+ | *** hazmat exhaust | ||
+ | ** Pump 2: 3010 fixed (calibration pump- circuit 11, butanol exhaust) | ||
+ | *** dP >= 500mbn | ||
+ | *** hazmat exhaust | ||
+ | ** Pump 3: Combined bypass lines (circuit 8) | ||
+ | *** dP small | ||
+ | *** 0.65 (MAB-AMS) + 5.61 (Ambient Bypass)= 6.26 lpm | ||
+ | ** Pump 4: PAM ancillary bypass (circuit 10a) | ||
+ | *** dP small | ||
+ | *** up to 1.7 (DustTrak) + 3.11-3.48 (PAM) + 0.6 (Valves Bypass) + 0.2 (PAM-AMS Inlet Bypass) = 5.66-5.98 lpm | ||
+ | ** Pump 5: MAB cyclone bypass (circuit 8) | ||
+ | *** dP small | ||
+ | *** 9.0-10.0 lpm | ||
+ | ** Pump 6: Perma-Pure dryer purge flow (circuit 10a) | ||
+ | *** dP ~ 100 mb | ||
+ | *** 5 lpm | ||
+ | *** 1.0 lpm | ||
+ | ** Pump 7: Inorganic Atomizer (calibratin pump, circuit 9) | ||
+ | ** Pump 8: Organic Atomizer (Circuit 11, propanol exhausted) | ||
== Tasks for Michael at the site == | == Tasks for Michael at the site == | ||
Line 66: | Line 197: | ||
** Check electrical connections with plug tester | ** Check electrical connections with plug tester | ||
** Label all the plugs in all trailers with the circuit number, if not already labeled. | ** Label all the plugs in all trailers with the circuit number, if not already labeled. | ||
− | ** Make power budget sheet for each trailer, post prominently | + | ** Make power budget sheet for each trailer, post prominently (Jochen may do ahead of time) |
+ | *** label every circuit at each trailer with circuit number and group | ||
** Check all pumps with DustTrak and portable CPC (need to borrow from Suzanne Hering) as they are being installed. | ** Check all pumps with DustTrak and portable CPC (need to borrow from Suzanne Hering) as they are being installed. | ||
** Post maps of Caltech and the local area, as well as hardware stores etc. in all trailers (next to door). | ** Post maps of Caltech and the local area, as well as hardware stores etc. in all trailers (next to door). | ||
Line 92: | Line 224: | ||
*Phone: 303.442.6481 | *Phone: 303.442.6481 | ||
*Estimated Cost: $2,811.67 | *Estimated Cost: $2,811.67 | ||
+ | |||
+ | === Housing === | ||
+ | * for 8 people (4 women, 4 men) | ||
+ | ** Men | ||
+ | *** Jose L. Jimenez | ||
+ | *** Michael Lechner | ||
+ | *** Patrick Hayes | ||
+ | *** (Mike Cubison with Aerodyne) | ||
+ | ** Women | ||
+ | *** Amber Ortega | ||
+ | *** Carly Robinson | ||
+ | *** Ingrid Ulbrich (arrive 5/19) | ||
+ | *** Delphine Farmer & Sanna until May 20; Raluca (from May 20) | ||
+ | *** (Donna Sueper with Aerodyne) | ||
+ | * final confirmation late April | ||
+ | * $133/night/apartment (2 apartments, 2 bedrooms each, 4 people/apartment) | ||
+ | ** 1: 5/4-6/18 210 N. Hudson Ave., Apt.# 2307, Pasadena, CA 91011 | ||
+ | ** 2: 5/8-6/18 820 Locust St., Apt.# 3102, Pasadena, CA 91101 | ||
+ | ** Note: same apartment complex, two different buildings - it was the best they could do for us | ||
+ | ** Location: [http://tinyurl.com/CityPlaceApts-Oakwood City Place Apartments] [http://tinyurl.com/CityPlaceApts 801 E. Walnut St, Pasadena, CA 91101] | ||
+ | ** Updates: Housing Share with the Murphy Group from UToronto. Two night overlap during Ingrid's arrival before Deline's departure. Raluca from the Murphy group (UToronto) will share a room with J-Group ladies after May 20. Raluca and Amber will coordinate payment - Murphy group pay 1/4 of the J-group apt (~$33/night) for ~20 nights. (Amber calculate Raluca total and see if she can pay Oakwood directly for a number of nights at the end). |
Latest revision as of 14:02, 6 August 2010
This page serves as documentation for organization of the Jimenez Group's participation in CalNex-LA. Do not confuse this page with the Main CalNex-LA page or the CalNex-LA Logistics page.
Contents
Tasks after CalNex-LA
- Repairs & upgrades
- Michael: quote on upgrade of 2x pump boxes (1 w/ 3x V301 controllers + higher rating of cables) & 2x automatic valves for inlet
- Carly: check with Varian on interlock signal on V70-prog_as_V301 controller (now inside pump box controlling pump 5)
- Michael: make sure we have 3x working RH probes and coupling hardware and that they work (working on it)
- Patrick + Amber: fix 3 us offset with PToF in lab AMS (try rebooting multiple times). Talk to Donna about software. (working on it)
- Patrick: calibrate all critical orifices, decide whether we need to order more (Waiting for Art to come back)
- Michael: make a couple more orifice fixtures
- Michael: replenishing O'Keefe orifices and fuses
- Michael: identify big stand-alone tool chest (lockable)
- Link
- Lockable
- Deep and Shallow drawers
- Ball Bearing drawer slides rated to 70lbs/drawer
- other stackable components if expansion is ever necessary
- Amber: Check channel 0 in Lab AMS slow board (and another channel)
- Modules are switched between Lab and C TPS.
- follow up on filament problem with TPS software (filament would go down) -- mention to Joel, try to reproduce
- Completed Post CalNex-LA Tasks
- Michael: Make map of east campus storage, and store location on group GPS
- Michael: order 1 1000-Torr baratron (1/2" tube connection) for Lab AMS.
- Michael: see when Varian guy is available after IAC (spinning, general pump stuff)
- (Move them here as they are completed, so that we all know that they have been completed)
- Carly: ask Thomas (cc Jose) where do we get special tool to remove module, and whether it is practical.
- Carly: test interlock on HIAPER, it works
- Amber + Patrick: clean lab AMS including fans (in pumps, electronics box, power supply, computer)
- Carly: replace pulser flange
- Carly: Replace MAB pump 5
Tasks in preparation for CalNex-LA
- Field kit
- SMPS comparison: Mike, Michael (run, analysis in progress)
- plywood bases for Ingrid's shelving racks? (Michael, confirm with Jose)
- inflatable mattresses (Jose will bring 2)
- Organization - Try to have ready by Mar 18 (next business mtg)
- Which AMSs to bring: MAB-AMS + LAB-AMS + C-AMS
- AMS alternation: PAM + TD: on LAB-AMS
- Ambient: 1min V, 1 min W
- PAM: same
- TD: same
- Need to set up + test Jayne switching valves: Mike + Amber (in progress)
- concentrator: Sanna will come 1st 2 weeks, she can send concentrator to CU in advance: we will use w/ MAB (Jose, Carly emailing with Sanna)
- Need a set of valves for concentrator: Carly w/ yellow - Amber will show her
- Need to be able to step vaporizer temperatures: Carly + Joel
- Inlet schematic for J-Group instruments: account for all fittings + tubing a priori: (Mike in progress). Include how to test for leaks and flows.
- logging computers are assigned to instruments - DONE (Mike)
- TSI software and Labview software can't run on the same computer
- logging computers are assigned to instruments - DONE (Mike)
- Put together 2x valve filtering system for inlets (3): (Delphine) (valves/tees/etc. found, set aside)
- Which SMPSs
- One in parallel with Lab-AMS, one in parallel with MAB-AMS, one as shared calibration system (comparison in progress, see above: Ingrid + Michael + Donna)
- OPC: Michael. software updated to report PM1, PM2.5, PM10; Mike has Igor code for analysis (see wiki)
- Radioactive source and chemical inventory and shipping: Michael
- waiting on Michelle; need to do reciprocity
- Gas requirements (current plan is to bring everything from CU; Carly, Amber will make sure we have it for packing)
- zero air (1 tank at a time, probably 2 tanks total) - Amber
- N2 (3 cylinders) - Amber
- SO2 cal gas - Amber
- research-grade N2 - Carly
- research-grade Ar - Carly
- research-grade Kr (2 lecture bottles) - Carly
- ICARTT sharing file organization (Ingrid + Donna)
- bother people about adding a sample file or readme saying they won't share data
- Driving our stuff there: Michael will rent truck on Friday, get CIRES parking pass (Penske).
- pick up truck Saturday, May 1
- load Sunday, May 2 at 10am Ingrid, Carly, Mike, Amber, Michael, Patrick, Art
- TO CalNex: Michael + Amber, departing Boulder May 3, arriving Pasadena May 4
- FROM CalNex: Michael + Mike, departing Pasadena June 18, arriving Boulder June 19
- Driving our stuff there: Michael will rent truck on Friday, get CIRES parking pass (Penske).
Power Breakdown for Jimenez Trailer at CalNex-LA
Will be updated when power is final - see google doc, ppt for latest
- PAM-TD-AMS related instruments
- Circuit 12A: 9.09 A
- HR-AMS 6.36 A, 700 W instrument
- Thermo Denuder (TD) 2.73 A, 300W
- Circuit 10B: 8.31 A
- PAM 6.8 A, 750 W (total, including lamp power supplies, MFCs, O3, RH, and SO2 monitors)
- Grimm OPC 0.2 A, 20 W
- TSI DMA #1 0.81 A, 90 W
- CPC 3010 #1 0.3 A, 33 W
- DustTrak 0.16 A, 18 W
- Circuit 12A: 9.09 A
- Shared Circuits
- Circuit 10A: 12.9 A
- Gast Pump for Perma Pure (by-pass) 5.45 A, 600 W
- Gast Pump for DT and OPC (by-pass) 5.45 A, 600 W
- UHSAS 2 A, 220 W
- Circuit 11: 16.35 A (butanol exhaust)
- Gast Pump (CPC 3010 #1) 5.45 A, 600 W
- Gast Pump (CPC 3010 #2) 5.45 A, 600 W
- Gast Pump (MAB Atmozier) 5.45 A, 600 W
- Circuit 10A: 12.9 A
- MAB-Concentrator Related Instruments
- Circuit 12B: 9.88 A
- Soft-Ionization (MAB) HR-ToF-AMS 6.36 A, 700 W instrument
- MAB Power supplies 0.53 A, 58 W
- MAB Discharge Supply 0.25 A, 27.5 W
- Concentrator Electronic Box 2.74 A, 300 W (estimated)
- Circuit 7: 15.7 A
- Concentrator Chiller 10.45 A, 1150 W
- Concentrator Saturator Heating Tape 5.24 A, 576 W
- Circuit 8: 15.21 A
- TSI DMA #3 0.81 A, 90 W
- CPC 3010 #2 0.3 A, 33 W
- Gast Pump (by-pass for MAB) 5.45 A, 600 W
- UV-APS 3.2 A, 350 W
- Circuit 12B: 9.88 A
- Independent Circuit
- Circuit 9: 6.86 A
- TSI Water CPC 3786 0.6 A, 66 W
- TSI DMA #2 0.81 A, 90 W instrument
- Gast Pump for Atomizer 5.45 A, 600 W
- Circuit 9: 6.86 A
- Updated(AMO 1635 PDT 16 May 2010)
Distribution of tasks while in the field
- This is the MASTER list (not the one in Google Docs)
- Power totals (Michael) -- also power table in field, sheets for borrowing parts
- EI-AMS (Patrick, Amber)
- PAM (inc. SO2, O3, RH, MFCs) (Amber)
- Thermal Denuder (Amber -- Mike will train Jose)
- MAB-AMS (Carly)
- C-AMS (probably won't bring)
- if bring, don't plan to operate, keep pumped in trailer
- possibly Darin could ship if we're desperate
- SMPS, CPC on Carly's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
- SMPS, CPC on Amber's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
- SMPS, CPC for calibration (operated as needed - AMS operator)
- Calibration CPC for ambient data (Mike, data reduction in field Michael/Ingrid)
- OPC (Michael w/Ingrid; igor code from Mike)
- DustTrak w/ PM1 inlet (Michael w/ Mike)
- TAG-AMS (Mike + Jose will support operation)
- UHSAS (Ping would bring, Delphine?)
- UV-APS (Alex could send, would do data)
- Downloading data from other instruments and model, making graphs and posting them (Ingrid)
- Uploading and plotting data in real-time: Ingrid, Donna
- Support: Delphine
Logging & pumping summary
- Logging computers: [duty cycles]
- Laptop 1: LabVIEW only, PAM inlet (best computer).
- Ozone monitor [low]
- Grimm [medium]
- DustTrak [low]
- RH monitor [low]
- Laptop 2: TSI AIM, PAM inlet
- Long-column 3010-based SMPS system
- Laptop 3: LabVIEW only, PAM inlet
- SO2 monitor (need more info on serial feed)
- lamp control (ditto)
- Laptop 4: LabVIEW only, MAB inlet
- TSI flowmeter on MAB SMPS [low]
- Yellow switching valve system [low]
- Can be one of the old black laptops
- Laptop 5: LabVIEW only, PAM inlet
- Jayne switching valve system [low-medium]
- TSI flowmeter on PAM SMPS [low]
- Labtop 6: TSI AIM, MAB inlet
- Long-column 3786-based SMPS system (MAB)
- Laptop 1: LabVIEW only, PAM inlet (best computer).
- Gast lab pumps
- Pump 1: 3010 scanning (ON MAB inlet - circuit 11, butanol exhaust)
- dP >= 500mb
- 1.0 lpm
- hazmat exhaust
- Pump 2: 3010 fixed (calibration pump- circuit 11, butanol exhaust)
- dP >= 500mbn
- hazmat exhaust
- Pump 3: Combined bypass lines (circuit 8)
- dP small
- 0.65 (MAB-AMS) + 5.61 (Ambient Bypass)= 6.26 lpm
- Pump 4: PAM ancillary bypass (circuit 10a)
- dP small
- up to 1.7 (DustTrak) + 3.11-3.48 (PAM) + 0.6 (Valves Bypass) + 0.2 (PAM-AMS Inlet Bypass) = 5.66-5.98 lpm
- Pump 5: MAB cyclone bypass (circuit 8)
- dP small
- 9.0-10.0 lpm
- Pump 6: Perma-Pure dryer purge flow (circuit 10a)
- dP ~ 100 mb
- 5 lpm
- 1.0 lpm
- Pump 7: Inorganic Atomizer (calibratin pump, circuit 9)
- Pump 8: Organic Atomizer (Circuit 11, propanol exhausted)
- Pump 1: 3010 scanning (ON MAB inlet - circuit 11, butanol exhaust)
Tasks for Michael at the site
- Immediately upon arrival at the site
- Check electrical connections with plug tester
- Label all the plugs in all trailers with the circuit number, if not already labeled.
- Make power budget sheet for each trailer, post prominently (Jochen may do ahead of time)
- label every circuit at each trailer with circuit number and group
- Check all pumps with DustTrak and portable CPC (need to borrow from Suzanne Hering) as they are being installed.
- Post maps of Caltech and the local area, as well as hardware stores etc. in all trailers (next to door).
- Pick up rental car (minivan)
- Not immediately, but during the study
- Collect samples of chiller water and the chemicals added to it. Discuss that people can sample them if needed. (Bring many small vials to distribute)
- Keep on top of butanol scrubbing for our CPCs
Rental Car
- AVIS
- Confirmation: 06665063US6
- Pick up Tuesday May 4th @ 4:00 pm (close at 6pm)
- Return Friday June 18th @ 9:00 am
- 570 North Lake Ave, Pasadena, CA 91101
- Phone: 626.449.6122
- Estimated Cost: $2,130.90
Rental Truck
- Penske
- Confirmation: 23002321
- Pick up Saturday May 5th
- Return June 19
- 2560 49th St. Boulder, CO 80301
- Phone: 303.442.6481
- Estimated Cost: $2,811.67
Housing
- for 8 people (4 women, 4 men)
- Men
- Jose L. Jimenez
- Michael Lechner
- Patrick Hayes
- (Mike Cubison with Aerodyne)
- Women
- Amber Ortega
- Carly Robinson
- Ingrid Ulbrich (arrive 5/19)
- Delphine Farmer & Sanna until May 20; Raluca (from May 20)
- (Donna Sueper with Aerodyne)
- Men
- final confirmation late April
- $133/night/apartment (2 apartments, 2 bedrooms each, 4 people/apartment)
- 1: 5/4-6/18 210 N. Hudson Ave., Apt.# 2307, Pasadena, CA 91011
- 2: 5/8-6/18 820 Locust St., Apt.# 3102, Pasadena, CA 91101
- Note: same apartment complex, two different buildings - it was the best they could do for us
- Location: City Place Apartments 801 E. Walnut St, Pasadena, CA 91101
- Updates: Housing Share with the Murphy Group from UToronto. Two night overlap during Ingrid's arrival before Deline's departure. Raluca from the Murphy group (UToronto) will share a room with J-Group ladies after May 20. Raluca and Amber will coordinate payment - Murphy group pay 1/4 of the J-group apt (~$33/night) for ~20 nights. (Amber calculate Raluca total and see if she can pay Oakwood directly for a number of nights at the end).