FLAME-3

From Jimenez Group Wiki
Revision as of 10:45, 10 September 2009 by Carly.robinson (talk | contribs) (Tentative Plan)
Jump to: navigation, search

This wiki page is a repository of logistical and organizational information for the FLAME-3 experiment, a collaborative experiment of CSU, Aerodyne, and CU. The official FLAME web page is here.

The wiki allows anyone to add or modify the information (after logging in, please contact Jose if you want to make changes and don't have an account on the wiki).

Dates and People

This information is kept on a Google Document, which can be viewed in 2 ways:

  • As a web page if you don't want to make changes or it has not been shared with you
  • As a Google Doc if it has been shared with you and you want to make changes

Instrumentation

FLAME-3 Plan
Group & PI Person Directly in Charge Instrument & Parameter Measured Power Space needed Confirmed or Tentative
CSU / S. Kreidenweis Taehyoung Lee and Laurie Mack HR-ToF-AMS (EI) 1 kW w/ pumps 25w X 32d X 45h (ft) Confirmed
CSU / S. Kreidenweis Kip Carrico SMPS 1 kW w/pump 2w X 2d X 6h (ft) Confirmed
CSU / S. Kreidenweis Kip Carrico Gas Analyzers (which ones?) ?? ?? Confirmed
CSU / S. Kreidenweis ?? Nephelometer ?? ?? Tentative
CSU / S. Kreidenweis ?? PTR-MS ?? ?? Tentative
CSU / S. Kreidenweis Amy Sullivan/Amanda Hilden Sunset continuous analyzer 2.5 kW w/pump 3w X 3d X 2h (ft) Confirmed
CSU / S. Kreidenweis Amy Sullivan/Amanda Hilden Filter samplers (hopefully in main chamber) 0.5 kW w/pump 2w X 2d X 5h (ft) Confirmed
ARI / T. Onasch ?? Li-Ion AMS ?? ?? Confirmed
ARI / T. Onasch ?? SP-AMS ?? ?? Confirmed
U. Manchester / G. McMeeking Gavin McMeeking SP2 550 W w/ pump (110 V, computer 240 V) 50w x 62d x 75h (cm) + floor space for pump Confirmed
U. Manchester / G. McMeeking Gavin McMeeking PASS 350 W w/ pump (240 VAC!) 50w x 62d x 60h (cm) + floor space for pump Confirmed
CU / J.L. Jimenez Carly Robinson MAB-AMS 1 kW w/ pumps Confirmed
CU / J.L. Jimenez Amber Ortega Thermal Denuder (on-off CSU AMS) 0.3 kW Confirmed
CU / J.L. Jimenez Amber Ortega PAM Chamber (on-off CSU AMS) 0.4 kW Confirmed
Carnegie Mellon / A. Robinson ?? ?? Mobile Lab w/ portable chamber (parked outside) Confirmed?

Tentative Plan

(10-Sept-09)Burn Schedulepdf

(from email from SK on 17-June-09): I suggest that we plan to arrive Sept 15 (that gives CSU 2 days to drive out, leaving Monday morning Sept 14) and spend a few days setting up. We will probably begin with a few stack burns to collect standard data for fuels we haven't done before (maybe repeat some other fuels) and getting the dilution system set up and tested. Then we can begin our chamber-burn dilution studies either that weekend or at the start of the following week.

That would give us 3 solid weeks for the studies (weeks of Sept 20, 27, Oct 4), which should be more than enough, and still be done before 15 October. In fact if it goes well we can probably pack up the weekend of Oct 3/4.

That plan might also allow us to stagger arrivals so some of you would not have to arrive to set up until a few days after the 15. You all know space is at a premium at the facility and some staggering may help us be less disruptive to the ongoing FSL operations.

Rental Cars and Other Vehicles

TBD

Lodging Info

Email from Clare Delaney to Sonia K on 19-June-09.

Smoke Jumper Dorms: The daily rate for the dorm rooms is $8.15 per day. If the stay lasts longer than 5 days it qualifies for a lower rate of $3.95 per day. The dorm fees can be made at the end of the stay and credit cards are the accepted form of payment. These are typical dorm rooms with twin beds and closets. We have 2,4, or 6 person rooms available with women on the first floor and men on the second. The showers and toilets are down the hall on each floor. A free washer and dryer are available to do laundry. Each tenant has access to the kitchen, which has several microwaves, stoves, & refrigerators. It's a good idea to be prepared to mark your food stuffs both dry and refrigerated. We have a limited number of utensils that most folks share. An added bonus is the workout facilities which include machines along with "free" weights. All in all it is a good option for your stay. Again when you firm up on who's coming, how long they plan to stay, and the exact dates of arrival letting me know would be great.