CalNex-JG

From Jimenez Group Wiki
Jump to navigationJump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

This page serves as documentation for organization of the Jimenez Group's participation in CalNex-LA. Do not confuse this page with the Main CalNex-LA page or the CalNex-LA Logistics page.

Tasks in preparation for CalNex-LA

  • Field kit
    • broken UPS (new one ordered, old one to be sent out once new box arrives) & check all UPSs (in process): Delphine
    • CPC 3010: Mike (called TSI, need paperwork from Michael -> Mike, send this week)
    • Orifices: Michael (start 3/19)
    • DMA Column: Mike (send back on Monday if not fixed by Mike on 3/19)
    • SMPS not scanning: Mike (analog problem?); could use in current state as calibration box
    • CPC comparison: Mike (tweaking labView code)
    • Sturdier foldable tables: Michael (Carly's guidance); still in process, have 2 to test ($59 each) get 4 more
    • Shelves + Racks: Ingrid (from home), Mike (from home), buy more?
    • add to the packing list things that don't go in boxes (tables, at least 7 chairs, etc.)
    • buy a large grey box for 3rd SMPS


  • Organization - Try to have ready by Mar 18 (next business mtg)
    • Which AMSs to bring: MAB-AMS + LAB-AMS + C-AMS
      • Follow up with Eben about LS: Mike (Jose emails Eben)
    • AMS alternation: PAM + TD: on LAB-AMS
      • Ambient: 1min V, 1 min W
      • PAM: same
      • TD: same
      • Need to set up + test Jayne switching valves: Mike + Amber (Friday 3/19)
      • concentrator: Sanna not sure if she can make it, she can send concentrator at least 2 weeks in advance: we will use w/ MAB (Jose will email Sanna)
      • Need a set of valves for concentrator: Carly w/ yellow - Amber will show her
      • Need to be able to step vaporizer temperatures: Carly
      • Inlet schematic for J-Group instruments: account for all fittings + tubing a priori: Carly + Amber (Delphine or Alex will dig out MILAGRO and/or BEARPEX). Include how to test for leaks and flows. Need to communicate
        • After assigning instruments to inlets, assign logging computers to instruments
          • TSI software and Labview software can't run on the same computer
    • Put together 2x valve filtering system for inlets (3): (Delphine) (valves/tees/etc. found, set aside)
    • Which SMPSs
      • One in parallel with Lab-AMS, one in parallel with MAB-AMS, one as shared calibration system ($Mike$ + Ingrid + Michael + Donna)
    • PTRMS sharing for PAM: Amber will contact Martin.Graus@nooa.gov
    • OPC: Michael. Mike will tweak software to report PM1, PM2.5, PM10.
    • Radioactive source and chemical inventory and shipping: Michael
    • Driving our stuff there: Michael will rent truck (Penske).
      • pick up truck Saturday, May 1
      • load Sunday, May 2
      • TO CalNex: Michael + Amber, departing Boulder May 3, arriving Pasadena May 4
      • FROM CalNex: Michael + Mike, departing Pasadena June 18, arriving Boulder June 19
    • Logging computers: Mike C.

Power Breakdown for Jimenez Trailer at CalNex-LA

  • PAM-TD-AMS related instruments
    • Circuit 1: 13.64 A
      • HR-AMS 6.36 A, 700 W instrument; 4.55 A, 500 W pumps
      • Thermo Denuder (TD) 2.73 A, 300W
    • Circuit 2: 13.95 A
      • PAM 6.8 A, 750 W (total, including lamp power supplies, MFCs, O3, RH, and SO2 monitors)
      • Grimm OPC 0.18 A, 20 W
      • TSI SMPS #1 6.81 A, 750 W, inc pumps
      • DustTrak 0.16 A, 18 W
  • Shared Circuit
    • Circuit 3: 12.25 A
      • Gast Pump (by-pass) 5.45 A, 600 W
      • TSI SMPS #2 6.81 A, 750 W, inc pumps
  • MAB-Concentrator Related Instruments
    • Circuit 4: 14.18 A
      • Soft-Ionization (MAB) HR-ToF-AMS 6.36 A, 700 W instrument; 4.55 A, 500 W pumps
      • MAB Power supplies 0.53 A, 58 W
      • Concentrator Electronic Box 2.74 A, 300 W (estimated)
    • Circuit 5: 15.7 A
      • Concentrator Chiller 10.45 A, 1150 W
      • Concentrator Saturator Heating Tape 5.24 A, 576 W
  • Independent Instruments
    • Circuit 6: 13.22 A
      • C-ToF-AMS 6.36 A, 700 W instrument
      • TSI Water CPC 3786 0.6 A, 66 W
      • TSI DMA 0.81 A, 90 W instrument
      • Gast Pump (for CPC) 5.45 A, 600 W
  • Note: We should request 7 circuits.(AMO 26 March 2010)

Distribution of tasks while in the field

  • This is the MASTER list (not the one in Google Docs)
  • Power totals (Michael) -- also power table in field, sheets for borrowing parts
  • EI-AMS (Patrick, Amber)
    • PAM (inc. SO2, O3, RH, MFCs) (Amber)
    • Thermal Denuder (Amber -- Mike will train Jose)
  • MAB-AMS (Carly)
  • C-AMS (Not sure if we will operate)
    • w/Light Scattering? (Not sure, depends on Eben)
  • SMPS, CPC on Carly's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
  • SMPS, CPC on Amber's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
  • SMPS, CPC for calibration (operated as needed - AMS operator)
  • Calibration CPC for ambient data (Mike, data reduction in field Michael/Ingrid)
  • OPC (Michael w/Ingrid; igor code from Mike?)
  • DustTrak w/ PM1 inlet (Michael w/ Mike)
  • TAG-AMS (Mike + Jose will support operation)
  • UHSAS (Ping would bring, Delphine?)
  • UV-APS (Alex could send, would do data)
  • Downloading data from other instruments and model, making graphs and posting them (Ingrid)
  • Uploading and plotting data in real-time: Ingrid, Donna
  • Support: Delphine

Logging & pumping summary

  • Logging computers: [duty cycles]
    • Laptop 1: LabVIEW only, PAM inlet.
      • Ozone monitor [low]
      • Grimm [medium]
      • DustTrak [low]
      • RH monitor [low]
    • Laptop 2: TSI AIM, PAM & MAB
      • Long-column 3010-based SMPS system (PAM)
      • Long-column 3786-based SMPS system (MAB)
    • Laptop 3: reserved for SO2 monitor until more info is known
    • Laptop 4: LabVIEW only, PAM & MAB
      • TSI flowmeter on MAB SMPS [low]
      • TSI flowmeter on PAM SMPS [low]
      • Can be one of the old black laptops
    • Laptop 5: LabVIEW only, PAM & MAB
      • Jayne switching valve system on PAM inlet [low-medium]
      • Yellow switching valve system on MAB inlet [low]
  • Gast lab pumps
    • Pump 1: 3010 scanning
      • dP >= 500mb
      • 1.0 lpm
      • hazmat exhaust
    • Pump 2: 3010 fixed
      • dP >= 500mb
      • hazmat exhaust
    • Pump 3: Combined bypass lines
      • dP small
      • 2.65 (PAM) + 0.6 (TD) + 0.2 (PAM-AMS) + 0.65 (MAB-AMS) = 4.1 lpm
    • Pump 4: PAM ancillary bypass
      • dP small
      • up to 1.7 (DustTrak) + 1.2 (Grimm) = 2.9 lpm
    • Pump 5: MAB cyclone bypass
      • dP small
      • 9.0-10.0 lpm
    • Pump 6: Perma-Pure dryer purge flow
      • dP ~ 100 mb
      • 5 lpm
      • 1.0 lpm

Tasks for Michael at the site

  • Immediately upon arrival at the site
    • Check electrical connections with plug tester
    • Label all the plugs in all trailers with the circuit number, if not already labeled.
    • Make power budget sheet for each trailer, post prominently.
    • Check all pumps with DustTrak and portable CPC (need to borrow from Suzanne Hering) as they are being installed.
    • Post maps of Caltech and the local area, as well as hardware stores etc. in all trailers (next to door).
    • Pick up rental car (minivan)
  • Not immediately, but during the study
    • Collect samples of chiller water and the chemicals added to it. Discuss that people can sample them if needed. (Bring many small vials to distribute)
    • Keep on top of butanol scrubbing for our CPCs

Rental Car

  • AVIS
  • Confirmation: 06665063US6
  • Pick up Tuesday May 4th @ 4:00 pm (close at 6pm)
  • Return Friday June 18th @ 9:00 am
  • 570 North Lake Ave, Pasadena, CA 91101
  • Phone: 626.449.6122
  • Estimated Cost: $2,130.90

Rental Truck

  • Penske
  • Confirmation: 23002321
  • Pick up Saturday May 5th
  • Return June 19
  • 2560 49th St. Boulder, CO 80301
  • Phone: 303.442.6481
  • Estimated Cost: $2,811.67

Housing

  • for 8 people (4 women, 4 men)
  • final confirmation late April
  • $133/night/apartment (2 apartments, 2 bedrooms each, 4 people/apartment)
    • 1: 5/4-6/18
    • 2: 5/8-6/18
  • Confirmed Group Members: Jose L. Jimenez, Carly Robinson, Amber Ortega, Mike Cubison, Michael Lechner, Patrick Hayes, Delphine Farmer, Ingrid Ulbrich
  • Requested Preferences:
    • Location: City Place Apartments 801 E. Walnut St, Pasadena, CA 91101
    • Amenities: Top/high floor units, facing garden/pool (not street)
    • Updates: Housing Share with the Murphy Group from UToronto. J-group ladies apt will have: Carly, Amber, Ingrid, + (Sanna or Delphine until May 20) + Raluca (from May 20 onwards). The Murphy group (UToronto) will have one apartment in the same complex, with Jen + Raluca + (Sanna or Delphine) until May 20. Raluca and Amber will coordinate payment - Murphy group pay 1/4 of the J-group apt (~$33/night) for ~20 nights (30 nights in the J-group apt minus the ~10 nights Sanna or Delphine will share with the Murphy group).