Tasks in preparation for CalNex-LA

  • Field kit
    • check all UPSs (in process): Delphine
    • CPC 3010: Mike (at TSI, checking on scanning capability)
    • Orifices: Michael (start 4/1ish)
    • CPC comparison: Mike (tweaking labView code)
    • SMPS comparison: Ingrid, Michael (run, analysis in progress)
    • Sturdier foldable tables: Michael (Carly's guidance); still in process, have 2 to test ($59 each) get 4 more
    • Shelves + Racks: Ingrid (from home), Mike (from home), buy more?
    • add to the packing list things that don't go in boxes (tables, at least 7 chairs, gas cylinders, etc.) (Carly)
    • buy clamps or racks for gas cylinders, cylinder cart (Michael)
    • binder with copies of MSDS's, radioactive paperwork (Michael)
    • check Wilson case (field kit team, 4/2 morning)
    • buy 2 24-V power supplies (Michael)
  • Organization - Try to have ready by Mar 18 (next business mtg)
    • Which AMSs to bring: MAB-AMS + LAB-AMS + C-AMS
    • AMS alternation: PAM + TD: on LAB-AMS
      • Ambient: 1min V, 1 min W
      • PAM: same
      • TD: same
      • Need to set up + test Jayne switching valves: Mike + Amber (in progress)
      • concentrator: Sanna will come 1st 2 weeks, she can send concentrator to CU in advance: we will use w/ MAB (Jose, Carly emailing with Sanna)
      • Need a set of valves for concentrator: Carly w/ yellow - Amber will show her
      • Need to be able to step vaporizer temperatures: Carly + Joel
      • Inlet schematic for J-Group instruments: account for all fittings + tubing a priori: (Mike in progress). Include how to test for leaks and flows.
        • logging computers are assigned to instruments - DONE (Mike)
          • TSI software and Labview software can't run on the same computer
    • Put together 2x valve filtering system for inlets (3): (Delphine) (valves/tees/etc. found, set aside)
    • Which SMPSs
      • One in parallel with Lab-AMS, one in parallel with MAB-AMS, one as shared calibration system (comparison in progress, see above: Ingrid + Michael + Donna)
    • OPC: Michael. software updated to report PM1, PM2.5, PM10; Mike has Igor code for analysis (see wiki)
    • Radioactive source and chemical inventory and shipping: Michael
      • waiting on Michelle; need to do reciprocity
    • Gas requirements (current plan is to bring everything from CU; Carly, Amber will make sure we have it for packing)
      • zero air (1 tank at a time, probably 2 tanks total) - Amber
      • N2 (3 cylinders) - Amber
      • SO2 cal gas - Amber
      • research-grade N2 - Carly
      • research-grade Ar - Carly
      • research-grade Kr (2 lecture bottles) - Carly
    • ICARTT sharing file organization (Ingrid + Donna)
      • bother people about adding a sample file or readme saying they won't share data
    • Driving our stuff there: Michael will rent truck (Penske).
      • pick up truck Saturday, May 1
      • load Sunday, May 2
      • TO CalNex: Michael + Amber, departing Boulder May 3, arriving Pasadena May 4
      • FROM CalNex: Michael + Mike, departing Pasadena June 18, arriving Boulder June 19

Power Breakdown for Jimenez Trailer at CalNex-LA

  • PAM-TD-AMS related instruments
    • Circuit 1: 13.64 A
      • HR-AMS 6.36 A, 700 W instrument; 4.55 A, 500 W pumps
      • Thermo Denuder (TD) 2.73 A, 300W
    • Circuit 2: 13.95 A
      • PAM 6.8 A, 750 W (total, including lamp power supplies, MFCs, O3, RH, and SO2 monitors)
      • Grimm OPC 0.18 A, 20 W
      • TSI SMPS #1 6.81 A, 750 W, inc pumps
      • DustTrak 0.16 A, 18 W
  • Shared Circuit
    • Circuit 3: 12.25 A
      • Gast Pump (by-pass) 5.45 A, 600 W
      • TSI SMPS #2 6.81 A, 750 W, inc pumps
  • MAB-Concentrator Related Instruments
    • Circuit 4: 14.18 A
      • Soft-Ionization (MAB) HR-ToF-AMS 6.36 A, 700 W instrument; 4.55 A, 500 W pumps
      • MAB Power supplies 0.53 A, 58 W
      • Concentrator Electronic Box 2.74 A, 300 W (estimated)
    • Circuit 5: 15.7 A
      • Concentrator Chiller 10.45 A, 1150 W
      • Concentrator Saturator Heating Tape 5.24 A, 576 W
  • Independent Instruments
    • Circuit 6: 13.22 A
      • C-ToF-AMS 6.36 A, 700 W instrument
      • TSI Water CPC 3786 0.6 A, 66 W
      • TSI DMA 0.81 A, 90 W instrument
      • Gast Pump (for CPC) 5.45 A, 600 W
  • Note: We should request 7 circuits.(AMO 26 March 2010)

Distribution of tasks while in the field

  • This is the MASTER list (not the one in Google Docs)
  • Power totals (Michael) -- also power table in field, sheets for borrowing parts
  • EI-AMS (Patrick, Amber)
    • PAM (inc. SO2, O3, RH, MFCs) (Amber)
    • Thermal Denuder (Amber -- Mike will train Jose)
  • MAB-AMS (Carly)
  • C-AMS (Not sure if we will operate)
    • w/Light Scattering? (Not sure, depends on Eben)
  • SMPS, CPC on Carly's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
  • SMPS, CPC on Amber's Inlet (operated by Mike, data reduction in field Michael/Ingrid)
  • SMPS, CPC for calibration (operated as needed - AMS operator)
  • Calibration CPC for ambient data (Mike, data reduction in field Michael/Ingrid)
  • OPC (Michael w/Ingrid; igor code from Mike?)
  • DustTrak w/ PM1 inlet (Michael w/ Mike)
  • TAG-AMS (Mike + Jose will support operation)
  • UHSAS (Ping would bring, Delphine?)
  • UV-APS (Alex could send, would do data)
  • Downloading data from other instruments and model, making graphs and posting them (Ingrid)
  • Uploading and plotting data in real-time: Ingrid, Donna
  • Support: Delphine

Logging & pumping summary

  • Logging computers: [duty cycles]
    • Laptop 1: LabVIEW only, PAM inlet.
      • Ozone monitor [low]
      • Grimm [medium]
      • DustTrak [low]
      • RH monitor [low]
    • Laptop 2: TSI AIM, PAM & MAB
      • Long-column 3010-based SMPS system (PAM)
      • Long-column 3786-based SMPS system (MAB)
    • Laptop 3: reserved for SO2 monitor until more info is known
    • Laptop 4: LabVIEW only, PAM & MAB
      • TSI flowmeter on MAB SMPS [low]
      • TSI flowmeter on PAM SMPS [low]
      • Can be one of the old black laptops
    • Laptop 5: LabVIEW only, PAM & MAB
      • Jayne switching valve system on PAM inlet [low-medium]
      • Yellow switching valve system on MAB inlet [low]
  • Gast lab pumps
    • Pump 1: 3010 scanning
      • dP >= 500mb
      • 1.0 lpm
      • hazmat exhaust
    • Pump 2: 3010 fixed
      • dP >= 500mb
      • hazmat exhaust
    • Pump 3: Combined bypass lines
      • dP small
      • 2.65 (PAM) + 0.6 (TD) + 0.2 (PAM-AMS) + 0.65 (MAB-AMS) = 4.1 lpm
    • Pump 4: PAM ancillary bypass
      • dP small
      • up to 1.7 (DustTrak) + 1.2 (Grimm) = 2.9 lpm
    • Pump 5: MAB cyclone bypass
      • dP small
      • 9.0-10.0 lpm
    • Pump 6: Perma-Pure dryer purge flow
      • dP ~ 100 mb
      • 5 lpm
      • 1.0 lpm

Tasks for Michael at the site

  • Immediately upon arrival at the site
    • Check electrical connections with plug tester
    • Label all the plugs in all trailers with the circuit number, if not already labeled.
    • Make power budget sheet for each trailer, post prominently.
    • Check all pumps with DustTrak and portable CPC (need to borrow from Suzanne Hering) as they are being installed.
    • Post maps of Caltech and the local area, as well as hardware stores etc. in all trailers (next to door).
    • Pick up rental car (minivan)
  • Not immediately, but during the study
    • Collect samples of chiller water and the chemicals added to it. Discuss that people can sample them if needed. (Bring many small vials to distribute)
    • Keep on top of butanol scrubbing for our CPCs

Rental Car

  • AVIS
  • Confirmation: 06665063US6
  • Pick up Tuesday May 4th @ 4:00 pm (close at 6pm)
  • Return Friday June 18th @ 9:00 am
  • 570 North Lake Ave, Pasadena, CA 91101
  • Phone: 626.449.6122
  • Estimated Cost: $2,130.90

Rental Truck

  • Penske
  • Confirmation: 23002321
  • Pick up Saturday May 5th
  • Return June 19
  • 2560 49th St. Boulder, CO 80301
  • Phone: 303.442.6481
  • Estimated Cost: $2,811.67

Housing

  • for 8 people (4 women, 4 men)
  • final confirmation late April
  • $133/night/apartment (2 apartments, 2 bedrooms each, 4 people/apartment)
    • 1: 5/4-6/18
    • 2: 5/8-6/18
  • Confirmed Group Members: Jose L. Jimenez, Carly Robinson, Amber Ortega, Mike Cubison, Michael Lechner, Patrick Hayes, Delphine Farmer, Ingrid Ulbrich
  • Requested Preferences:
    • Location: City Place Apartments 801 E. Walnut St, Pasadena, CA 91101
    • Amenities: Top/high floor units, facing garden/pool (not street)
    • Updates: Housing Share with the Murphy Group from UToronto. J-group ladies apt will have: Carly, Amber, Ingrid, + (Sanna or Delphine until May 20) + Raluca (from May 20 onwards). The Murphy group (UToronto) will have one apartment in the same complex, with Jen + Raluca + (Sanna or Delphine) until May 20. Raluca and Amber will coordinate payment - Murphy group pay 1/4 of the J-group apt (~$33/night) for ~20 nights (30 nights in the J-group apt minus the ~10 nights Sanna or Delphine will share with the Murphy group).