ARCTAS

From Jimenez Group Wiki
Revision as of 00:06, 22 January 2008 by Jose (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

The purpose of this page is to serve as a repository of schedules and information for the participation of the Jimenez group in the ARCTAS campaign.

Schedules should be kept in most detail here, as the group calendar is often too crowded.

Integration Phase

(inclusive dates):

  • 2/22: Truck leaves Boulder with AMS and rest of kit
  • 3/4: AMS goes onto the plane
  • 3/12: Power check
  • 3/17: Safety Brief
  • 3/18-3/21: Test Flights
  • 3/23-3/29: No access
  • 3/30-3/31: Packing plane
  • 1/4: Transit to AK (Mike)


Unfortunately the power check is right between our integration date and the test flights, so Mike will either 1) stay on after integ, 2) stay from power check to test flights, or 3) fly out for the day.

Fairbanks Phase

Details to go here.

Summer Phase

Details to go here.